Thorpe Park Business Park
Overview
RFM Group were commissioned and appointed in early January 2019 by Wainwright & CO to refurbish the head office accommodation for a private client at Thorpe Park Business Park, to enable brand new additional spaces for our client, improving and enhancing working conditions and wellbeing.
Our approach
Over a 20-week period, the project included refurbishment and fit-out of the full ground floor, all stairs and toilet cores and reinstallation of the plant room.
- Full strip-out and refurbishment
- Brand new heating and cooling
- Major plant modifications and plant replacements
- Brand new toilets, kitchen, reception area, lift landing areas, flooring and decoration
Industry
Office
Sector
Commercial
Project value
£1.2 Million
Project Timescale
20 weeks
Outcome
We successfully delivered the project on time and within budget for a delighted client through our SQS promise:
Service
Before commencing on site, RFM had fulfilled a detailed health assessment of our Construction Phase Plan. This included a Traffic Management Plan, Health and Safety Site Audits and Daily signing in and out registers for all staff visiting site.
Quality
Works were sequenced to ensure minimum disruption to our clients’ employees whilst allowing full business continuity. All approved contractors went through a full induction before project commencement, adhering strictly to RFM Groups and our client’s policies and procedures.
Service
In April 2019, we achieved a monthly Health & Safety audit score of 98.7% which is evidence of our uncompromising approach to Health & Safety.
Paul Mulhearn, Managing Director
“We were very pleased to complete and fulfil this project for our client, achieving Service, Quality, Safety to an outstanding level. Our client’s employees are now benefiting from brand new spaces of which they can work and relax in. We look forward to working with our client in years to come.”