Commercial Estates Group CEG, Altrincham

Overview

Centric were selected to upgrade and refurbish a commercial property in Edward Court, Altrincham on behalf of Commercial Estates Group (CEG).

The property group Commercial Estates Group (CEG) manage a property portfolio covering six million sq ft valued at around £800 million. Their rental income is £50 million, with an estimated rental value of around £80 million.

The clients required Centric to refurbish the first floor creating three offices each with a meeting room and refreshment area. Other elements included:

  • All fittings and furniture installed.
  • On the ground floor we created male and female changing rooms and showers.
  • Externally we installed a bike shelter and associated paving works.
  • Minor decoration to the lobby areas.

Our approach

Centric used a highly trained Site Manager and Surveyor to oversee the project. We utilised our inhouse project management process and scheduling system to ensure a co-ordinated project plan was adhered to.

Works Undertaken Included:

  • Full strip-out and alterations
  • New lighting and cabling installations
  • New showers and changing rooms
  • Anti-static carpet tiles
  • New partitioning
  • Raised floor and new floor finishes
  • New suspended ceilings
  • New mechanical electrical installations
  • New bike racks and store
  • Painting and Decorating
  • Blinds
  • Refreshment areas
  • Sanitaryware
  • Building works
  • Waterproofing
  • Fitted fixtures and fittings
  • Fencing
  • Landscaping

Industry

Office administration

Sector

Commercial

Project Value

£230,000

image

Outcome

The refurbished building was completed to a very high standard, ready for three businesses to move straight into. The modern décor and amenities complimented by additional facilities such as shower room and bike storage will help ensure optimal rental income for the landlord.

Keys Feature Include:

  • Feature double height receptions
  • Full access raised floors
  • Recessed Low Energy Lighting
  • Air conditioning
  • On site security and CCTV

Covid-19 restrictions were in place during the project. This required Centric to modify our operations to ensure the continued safety of everybody onsite. Thorough risk assessments and Covid-19 safety protocols were implemented. Centric were able to call upon our Facilities Management division to provide extra expertise.

Gallery.  Gallery.  Gallery.  Gallery.  Gallery.  Gallery.  Gallery.  Gallery.  Gallery. 
Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.Start with a conversation.
End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.End with a space you love.
Contact us. Contact us. Contact us. Contact us.
icon